Path: cantaloupe.srv.cs.cmu.edu!rochester!udel!bogus.sura.net!news-feed-1.peachnet.edu!umn.edu!lynx.unm.edu!q5022531.mdc.com!user
From: Cohen@ssdgwy.mdc.com (Andy Cohen)
Newsgroups: sci.space
Subject: Report on redesign team
Followup-To: sci.space
Date: 27 Apr 1993 14:30:35 GMT
Organization: MDA-W
Lines: 172
Distribution: world
Message-ID: <Cohen-270493073219@q5022531.mdc.com>
NNTP-Posting-Host: q5022531.mdc.com

The following is what they feed to us..... most has been posted already,
but there are a number of items not seen here yet.....

Redesign Activities Update -- Following is the weekly status on redesign,
based on information provided by NASA headquarters.

The station Redesign Team (SRT) provided a detailed status report to the
Advisory Committee on the Redesign of the Space Station on April 22.  The
day-long meeting was held in ANSER facilities in Crystal City, VA; topics
covered by the SRT included a preliminary mission and goals statement for
the space station; science, technology and engineering research; the
assessment process; and the design approach. Discussions on management
options and operations concepts also were held.

The Design Teams then presented the three options under study:

¥ Option A - Modular Buildup -- Pete Priest presented the A option. Priest
said the team is working to define a station that meets cost goals and has
identified three distinct phases of evolution - power station, human tended
and permanent presence. The team will define the minimum capability needed
to achieve each phase, the total cost of each phase and the achievable
capability for budget levels. The A option uses current or simplified
Freedom hardware where cost effective and is considering other existing
systems such as the so-called "Bus-1 spacecraft," the orbiter and Spacelab.

The Power Station Capability could be achieved in 3 flights with Freedom
photo voltaic modules providing 20 kW of power. 30-day Shuttle/Spacelab
missions docked to the power station are assumed for this phase.

Human Tended Capability would be provided by the addition of the U.S.
Common Module Module which adds subsystems and 9 payload racks and docking
ports for ESA and Japanese laboratories. 60-day missions with the orbiter
docked to the station are assumed for this phase. Different
operation/utilization modes are being studied for this phase.

¥ Option B - Freedom Derived -- Mike Griffin presented the status of Option
B activities. Griffin detailed the evolution of the Freedom-derived option,
from initial Research Capability, to Human-Tended Capability, to Permanent
Human Presence Capability, to Two Fault Tolerance, and finally Permanent
Human Capability. Griffin also outlined proposed systems changes to the
baseline program, with minor changes to the Communications and Tracking
system, Crew Health Care System and ECLSS, and a major change to the Data
Management System.

Initial Research Capability would be achieved with 2 flights to 28.5 degree
inclination (3 flights to 51.6 degrees) and consist of an extended duration
orbiter-Spacelab combination docked to a truss segment with 2 photo voltaic
arrays providing 18.75 kW of power.

Human-Tended Capability would be achieved in 6 flights and add truss
segments and the U.S. lab.

Permanent Human Presence Capability would be achieved in 8 flights with two
orbiters providing habitation and assured crew return.

Two Fault Tolerance, achieved in 11 flights, would build out the other
section of truss with another set of PV modules, thermal control and
propulsion systems.

The freedom derived configuration could achieve an International Complete
state with 16 flights.  Three more flights, to bring up the habitat module,
a third PV array and two Assured Crew Return Vehicles (ACRV) would complete
the Permanent Human Capability with International stage.

Griffin told the Redesign Advisory Committee that eliminating hardware
would not, by itself, meet budget guidelines for the Freedom derived
option.  Major reductions or deferrals must occur in other areas including
program management, contractor non-hardware, early utilization and
operations costs, he said.

¥ Option C - Singe Launch Core Station -- Chet Vaughn presented Option C,
the Single Launch Core Station concept.  A Shuttle external tank and solid
rocket boosters would be used  to launch the station into orbit.  Shuttle
main engines would be mounted to the tail of the station module for launch
and jettisoned after ET separation.

The module, 23 feet in diameter and 92 feet long, would provide 26,000
cubic feet of pressured volume, separated into 7 "decks" connected by a
centralized passageway.  Seven berthing ports would be located at various
places on the circumference of the module to place the international
modules, and other elements.  This "can" would have two fixed photo voltaic
arrays producing approximately 40 kW of power flying in a solar interial
attitude.

In his closing comments to the Redesign Advisory Committee, Bryan O'Connor
said a design freeze would be established for the 3 options on April 26 so
that detailed costing of the options can begin.  The next meeting with the
Redesign Advisory Committee will be May 3.

Russian Consultants Arrive in U.S. -- A delegation of 16 Russian space
experts arrived in the U.S. on April 21 and briefings to the SRT by members
of the Russian team began on the 22nd.  The group includes Russian Space
Agency General Director Y. M. Koptev, and V. A. Yatsenko, also of the RSA. 
Others on the team include representatives from the Ministry of Defense,
the Design Bureau SALYUT, the Institute of Biomedical Problems, the
Ministry of Foreign Affairs, NPO Energia and TsNIJMASH.  The Russian team
briefed the SRT on environmental control and life support system, docking
systems, the Proton launch vehicle, Mir operations and utilization, and the
Soyuz TM spacecraft.

The Russian consultants are available to the SRT to assess the capabilities
of the Mir space station, and the possible use of Mir and other Russian
capabilities and systems as part of the space station redesign.  They will
be available to the SRT through May 5.

Management and Operations Review Continues --  Work continued in the SRT
subgroups.  The Management Group under Dr. Walt Brooks is working to
develop a family of options that solve the current problems and build a
foundation for the transition to development and operations.  Various
management options have been developed including:

¥ Lead Center with the Center Director in the programmatic chain of
command.

¥ Host Center with the Program Manager reporting directly to an Associate
Administrator.

¥ Skunk Works/Dedicated Program Office with a small dedicated co-located
hand-picked program office.

¥ Combine Space Station with Shuttle, with the space station becoming an
element of the current program.

¥ Major Tune Up to Current Organization, with current contracts and
geographical distribution maintained but streamlined.

The Operations Group under Dr. John Cox is building on the work of the
Operations Phase Assessment Team lead by Gene Kranz of NASA-JSC, which had
already begun a comprehensive review of operations and had concluded in its
preliminary results that significant cost reductions are possible.

As part of its work,  the Operations Group has identified teams of agency
experts to develop detailed evaluations of each design in the areas of
assembly and operations, utilization, maintenance and logistics and testing
and ground operations.

What's in the Week Ahead? -- The Design Support Teams will provide a
comprehensive status of their option to the Station Redesign Team on Monday
and Tuesday at which point the design will be "frozen" to begin the
detailed cost assessment.   Also this week, the team will begin preparing
for the next round of discussions with the redesign Advisory Committee, to
be held May 3.

Dr. Shea Steps Down --  Dr. Joe Shea stepped down as director of the
Station Redesign Team on April 22 and Bryan O'Connor will take over the
activities of the team.  Dr. Shea submitted his resignation as assistant
deputy administrator for space station analysis, but will continue to serve
as a special advisory to NASA Administrator Goldin and be available to
consult with the SRT. Mr Goldin accepted the resignation so that a request
from Dr. Shea to reduce his workload could be accommodated.

Key Milestones -- The key dates for the SRT as they are currently being
carried on the schedule are:

April 26
Design Freeze on Options for Costing

April 27
Design Support Team Present Selected Options to SRT

May 3
Status report to Redesign Advisory Committee

May 15
Interim report by Redesign Advisory Committee

June 7
Final report to Redesign Advisory Committee


(Oct. 31-cancellation .....just my opinion...AC)
 
